347/600V Switchgear: Procurement and Submittal Checklist
A 347/600V designation is a starting point for a purchase, not proof that an assembly or its protective devices suit a particular system.
DIRECT FROM THE MANUFACTURER / NEW EQUIPMENT

THE MANUFACTURER’S PERSPECTIVE — 02
A 347/600V designation is a starting point for a purchase, not proof that an assembly or its protective devices suit a particular system. For a new distribution lineup, the most useful request combines the electrical design with physical, documentation and delivery requirements. An engineer and the direct manufacturer can then identify what is feasible, what remains unverified and which details must be resolved before release.
Describe the source and system configuration
Provide a current one-line diagram showing the source, transformer connections, main device, feeders and any alternate source or tie. A 347/600V wye description normally distinguishes the nominal line-to-neutral voltage from the line-to-line voltage; identify the phase, wire and grounding arrangement rather than relying on the label alone. Include utility requirements where the lineup serves the service entrance.
Ask the manufacturer to evaluate the actual system voltage and grounding configuration against the proposed assembly, insulation, bus supports, disconnects, protective devices and connected instruments. A component suitable for a different system should not be assumed suitable here. Identify control-power sources and any separately derived supply so their ratings and connection boundaries are reviewed as well.
Put electrical duty on the request
Send a load schedule with the main and feeder continuous-current requirements, expected demand, motor or nonlinear loads and documented expansion plans. Specify neutral requirements, including any engineering assessment of nonlinear-load effects. Available space for a future feeder is not the same as confirmed bus capacity; ask for each to be identified separately in the offer.
Provide the available fault-current study or the best source data and assumptions available at the connection point. Request assembly short-circuit and, where applicable, short-time withstand information along with device interrupting ratings. The design engineer must compare ratings with the calculated duty and clearing times; a high interrupting rating on one breaker does not establish the rating of the entire assembly.
Define connections and installation constraints
Include a room or site plan with door routes, equipment footprint limits, access needs and cable entry direction. For each connection, identify conductor material, size, quantity and termination responsibility, or flag them as pending. A compact lineup can reduce floor space but may leave less room for cable bending, terminations or future changes.
Describe indoor or outdoor placement, ambient conditions, moisture, corrosive exposure and any required enclosure features. Coordinate foundation, anchorage, shipping splits, receiving and lifting with the contractor and structural team. The manufacturer needs these interfaces early because section dimensions and shipping arrangements can affect both the proposal and the field installation plan.
Make proposals comparable
State the intended assembly type, applicable project standards, required approval or listing, device preferences, metering and monitoring functions. If a switchboard is appropriate, ask whether the proposed assembly carries the project-specific listing required under UL 891; that standard should not be treated as a blanket listing for every kind of switchgear. Verify the actual construction and documentation.
Request an itemized scope and a clearly marked exceptions list. Compare the number and types of feeder devices, spare provisions, enclosure construction, metering, testing and freight rather than price alone. Identify who provides cables, field connections, utility coordination, protective-device settings, commissioning and permits; an omitted interface can move significant work to another contract.
Review the submittal against the design
Ask for a one-line, equipment elevations and plan, dimensions, weights, terminal and cable-entry details, device schedules and applicable ratings. Control schematics, terminal-block details and a communications point list may also be needed. Check that the neutral and grounding interfaces shown match the design and that the equipment fits the approved site arrangement.
Have the engineer review proposed protective devices, available-fault assumptions and coordination-study inputs, including trip functions and any required settings. Ask for relevant listing evidence, catalog information and a bill of materials with proposed substitutions identified. Return a consolidated review identifying approval, exceptions and open questions; an approval should not conceal unresolved rating or interface assumptions.
Link approvals, testing and delivery
Build the schedule around drawing submission, review and revision, engineering release, component procurement, fabrication, inspection and shipment. Ask which decisions or long-lead components control the proposed schedule and how changes affect it. Confirm the requested delivery window and handling requirements without treating an initial estimate as a guarantee.
Define factory inspection or functional test scope, witness requirements, acceptance criteria and records before ordering. At turnover, request final drawings, equipment instructions and agreed test reports, with outstanding field work clearly assigned. Qualified electrical personnel should plan installation, verification and energization under applicable site procedures, codes and manufacturer instructions; the purchasing checklist is not an operating procedure.