AMERICAN-BUILT POWER DISTRIBUTIONSAN ANTONIO & SOUTH TEXAS / NATIONWIDE SHIPPING

BUILT IN THE USA. READY FOR YOUR PROJECT.

Planning New Equipment for Retrofits

A retrofit is more than placing a new lineup where an existing one stood.

DIRECT FROM THE MANUFACTURER / NEW EQUIPMENT

Row of Allen-Bradley electrical control cabinets with black handles.
01 / POWER DISTRIBUTIONBUILT FOR THE JOB
Representative switchgear photography.
✦MADE IN THE USAAmerican components
▦UL 891Switchboards when specified
↗BUILT TO SPECProject-specific engineering
→NATIONWIDEShipping across the USA

THE MANUFACTURER’S PERSPECTIVE — 02

A retrofit is more than placing a new lineup where an existing one stood. The new assembly must fit the facility’s electrical system, building constraints and planned outage sequence. Facility owners, specifying engineers and contractors can reduce surprises by defining those interfaces before purchasing, then keeping manufacturer drawings and the field installation plan aligned as the design develops.

Establish a reliable starting point

Gather the current one-line diagram, load schedules, equipment nameplate information, available drawings and records of modifications. Identify every source, including generators, ties and any backfeed, along with the circuits that must remain in service. Older drawings are useful leads, not proof that every conductor and protective device remains as shown.

Have the engineer and qualified site personnel reconcile the documents with conditions that can be verified safely. Record discrepancies and assumptions in a common register. If a feeder destination or source capacity is uncertain, resolve it before the equipment design is frozen; an overlooked interface can affect both the lineup and the outage plan.

Match the electrical system, not just the footprint

The quotation request should identify system voltage, phase and wire arrangement, grounding configuration, load and demand information, and proposed main and feeder circuits. The specifying engineer should also provide available fault-current information and protection requirements for the proposed location, including contributions from alternate sources where relevant.

A lineup that fits the room is not automatically suitable for its system. The engineer must evaluate assembly duty, device interrupting ratings, protective coordination and any planned growth together. Retaining existing feeders may constrain device choices and termination space; adding future capacity can increase footprint and cost without solving present interface limitations.

Survey space and connection routes

Document the usable footprint, ceiling height, doorways, delivery path and required working and maintenance clearances. Capture the locations of walls, columns, drains and ventilation, as well as floor or pad conditions. The contractor and engineer should verify actual dimensions and applicable clearance requirements rather than assuming the former equipment’s position is adequate.

For each incoming and outgoing circuit, establish top or bottom entry, conductor quantities and sizes, termination locations and bending-space needs. Existing cable length and routing may limit where connections can be made. If busway or a transformer connects directly, coordinate its orientation, supports and connection details with the equipment suppliers.

Plan construction around facility continuity

The owner should identify critical loads, acceptable interruption windows and stakeholders who must approve the work. With the contractor and engineer, compare a single planned outage with phased installation. Phasing may keep portions of the facility operating, but can add temporary connections, construction boundaries, testing and coordination between stages.

Where temporary power is needed, define its capacity, connection points, protection, grounding and transfer arrangements through project engineering. Assign responsibility for permits, utility coordination, temporary equipment and restoration. A written sequence and contingency plan should address dependencies and recovery decisions without substituting for site-specific safety procedures.

Define the purchase and review package

Request a proposal for the new assembly with the one-line, verified site dimensions, circuit schedule, environmental conditions, required delivery destination and desired milestones. Specify the applicable equipment standard and any project-required listing. For a switchboard, UL 891 may be relevant; confirm the actual assembly’s listing and scope for the project.

Compare proposals by device functions, electrical duty, enclosure, metering, drawings, testing and clearly stated exceptions, not just the equipment price. Ask who supplies field cabling, foundations, control connections and protection settings. Review manufacturer submittals against the latest site information before approval, and track design changes and their schedule implications.

Coordinate handoff, testing and energization

Agree on shipping splits, lifting information, sectional interfaces and receiving arrangements early enough for the contractor to plan access. Identify required shop drawings, connection diagrams, test records and operating manuals in the purchase documents. Assign owners for field installation checks, protection studies, settings and any required authority or utility inspections.

The owner coordinates the outage and authorizes the site work; qualified electrical personnel perform installation, verification and energization under applicable codes, site procedures and manufacturer instructions. Before turnover, reconcile field changes with final drawings, document test results and resolve open items. Build review, component availability, delivery and commissioning into the schedule rather than assuming a fixed lead time.

LET'S BUILD SOMETHING RELIABLE — 03

Ready to talk
switchgear?

Tell us about the new equipment your project needs. Include as much or as little detail as you have today.

(951) 403-5738

CALL TO DISCUSS YOUR PROJECT

PROJECT INQUIRY

Request a quote

01 — 04

This opens your email app for you to review and send. Add any details that do not transfer, or call if you do not have an email app configured.

Request a quote