Automatic Transfer Switches: One-Line and Feeder Planning
An automatic transfer switch (ATS) connects selected loads to one of two sources when the normal supply is unavailable and the alternate source is acceptable.
DIRECT FROM THE MANUFACTURER / NEW EQUIPMENT

THE MANUFACTURER’S PERSPECTIVE — 02
An automatic transfer switch (ATS) connects selected loads to one of two sources when the normal supply is unavailable and the alternate source is acceptable. The one-line diagram is the starting point for deciding what transfers, how each source is protected, and where the new assembly fits. For owners, engineers, and contractors, those decisions also shape the purchase scope and installation schedule.
Draw both sources and every destination
Show the normal source, alternate source, transfer switch, upstream disconnecting and protective devices, and downstream distribution. Identify each feeder by destination rather than labeling everything simply “emergency.” A generator may serve several transfer switches, while a second utility-derived source may require a different interconnection arrangement. Include transformers, ties, and any other paths that could energize the system.
Mark which loads must remain available and which can wait for normal power. One large ATS serving a common distribution section can simplify the source connection, but it may transfer nonessential load too. Multiple switches can separate priorities and allow different operating sequences, at the expense of additional equipment, wiring, coordination, and space.
Match feeder demand to both supplies
Provide a load schedule with present demand, connected loads, operating patterns, and the proposed future additions for each transferred feeder. Include large motor starting requirements and other step loads, not just nameplate totals. The design engineer can assess whether the alternate source can accept the sequence of loads without unacceptable voltage or frequency effects.
Record system voltage, phase and wire configuration, and the required continuous current for the ATS and its connections. The transfer equipment must be suitable for the actual source and load characteristics, including applicable motor or other special-duty requirements. Reserving capacity for growth can increase initial equipment size, but a spare feeder position alone does not establish source or transfer-switch capacity.
Coordinate fault duty and the neutral
Supply available short-circuit current and protective-device information for both sources at the ATS location. The engineer must compare those conditions with the proposed transfer equipment’s short-circuit current rating and its associated protective-device and clearing conditions. An ATS is not automatically the feeder overcurrent protection; identify that protection on the one-line and review coordination with downstream devices.
Show the neutral and grounding arrangement separately from the phase paths. A solid neutral and a switched neutral have different implications for ground-fault sensing and whether an alternate source is treated as separately derived. The engineer of record should resolve source bonding, pole configuration, and ground-fault protection under the applicable code and project-specific source arrangement.
Specify the transfer sequence and controls
Describe when the ATS should request generator start, what constitutes an acceptable alternate source, any load sequencing, and the desired return to normal power. Open-transition transfer interrupts the load during the changeover. If a project considers closed transition or another special sequence, synchronization, source-paralleling permissions, equipment capability, and protection require explicit review.
Define the interfaces between the transfer controller, generator controls, and building monitoring system. List start contacts, source and switch position indications, alarms, communications protocol, and the party responsible for control wiring and programming. Agree on control-power arrangements and expected behavior when a source or control supply fails; a one-line alone rarely captures all of this logic.
Make conductor and maintenance interfaces buildable
Show source and load cable entry directions, conductor material, size and quantity per phase, neutral and equipment grounding conductors, and required termination details. The proposed enclosure must accommodate cable bending space and accessible connections. Coordinate the footprint, door swing, ventilation, applicable working clearances, and the delivery route with the contractor before approving drawings.
If continuity during transfer-switch maintenance matters, ask whether a bypass-isolation arrangement is appropriate and available for the specified duty. It adds space, components, and cost; its actual operating states and isolation features must be verified rather than assumed. Qualified personnel should plan maintenance and site isolation using approved procedures and the equipment instructions.
Turn the one-line into a purchase package
Send the direct manufacturer the current one-line, load schedule, source and fault data, layout constraints, control sequence, applicable specifications, and requested equipment listings. Confirm the listing and ratings for the proposed transfer equipment and any associated assembly; do not assume a switchboard listing covers the ATS. For projects in San Antonio, South Texas, or elsewhere, identify any utility and authority approval interfaces.
Request a proposal identifying included devices, enclosure, drawings, factory checks, exceptions, and field connections. Agree who provides protective settings, installation, commissioning, and final records. Allow time for engineering review, drawing approval, component availability, fabrication, and coordinated outage planning; changes to source capacity or feeder routing after approval can affect the schedule and scope.