Selective Coordination Basics

Selective coordination is a design objective: when an overcurrent occurs, the protective device nearest the affected portion of the system operates while upstream devices remain closed, preserving power to unaffected loads.

DIRECT FROM THE MANUFACTURER / NEW EQUIPMENT

Tall gray switchgear cabinets with circuit breakers and orange labels on pallets.
01 / POWER DISTRIBUTIONBUILT FOR THE JOB
Representative switchgear photography.
✦MADE IN THE USAAmerican components
▦UL 891Switchboards when specified
↗BUILT TO SPECProject-specific engineering
→NATIONWIDEShipping across the USA

THE MANUFACTURER’S PERSPECTIVE — 02

Selective coordination is a design objective: when an overcurrent occurs, the protective device nearest the affected portion of the system operates while upstream devices remain closed, preserving power to unaffected loads. Achieving it requires more than choosing adjustable breakers. Engineers, contractors, and owners need a study that considers actual devices, fault-current ranges, operating modes, and the continuity requirements of the project.

Start with the loads and the required scope

A fault on one feeder should not necessarily disconnect an entire building. In a coordinated arrangement, that feeder’s protective device clears the fault without unnecessarily opening the main. A fault on the main bus, however, may require the main or an upstream device to operate; coordination cannot preserve power to equipment within the faulted zone.

The engineer should identify which circuits need coordination, the overcurrent range to be covered, and the applicable code, specifications, and authority requirements. Some requirements call for selective coordination across the full range of overcurrents; a narrower contractual target is not a substitute where broader coordination is required. Record the intended source configurations and operating states as well.

Read time-current curves as bands, not promises

Time-current curves plot current against operating time, typically on logarithmic scales. Breaker and fuse characteristics appear as bands because their response varies within stated tolerances. A study compares the downstream and upstream characteristics, on a common current and voltage basis where necessary, to assess whether the downstream device can clear before the upstream device operates.

Curves must be checked against actual settings, sensor or trip ratings, and device types. Apparent separation at one point does not establish coordination everywhere, particularly near instantaneous operating regions or at high fault currents. The engineer also checks that protection permits expected transformer energization and motor starting without sacrificing the required fault response.

Define the fault range for every source

The study needs a current one-line, utility fault information and transformer impedances, conductor lengths and characteristics, and relevant motor contributions. From these inputs the engineer determines available fault currents at the locations being evaluated, including minimum and maximum conditions where appropriate. Both the magnitude and type of fault matter to the protective functions being assessed.

A standby generator, utility source, or different tie position can change the current seen by the same device. Lower fault current may delay operation or fall below a pickup; higher current may cause upstream instantaneous operation. Evaluate each credible arrangement instead of assuming that coordination under the normal utility source also holds during transfer or maintenance configurations.

Check device data and coordination limits

Time-current curves alone may not capture how current-limiting devices interact during very fast faults. Where applicable, the engineer should consult the device manufacturer’s published coordination or selectivity tables and supporting test information for the exact device pair, settings, system conditions, and stated current limit. Do not extrapolate a table to a different combination without documented support.

Coordination is separate from interrupting rating and assembly short-circuit capability. Each device and the complete assembly must still be suitable for the available duty under the applicable design and product requirements. For ground-fault protection, review sensing arrangements and device interactions separately; phase-current curves alone may not establish ground-fault coordination.

Balance continuity, protection, and equipment choices

Increasing an upstream delay can improve separation from a downstream curve, but it can also increase fault duration and affect equipment withstand or arc-flash exposure. Adjustability, selectivity limits, maintainability, space, and project budget should be evaluated together. A study provider must assess the proposed settings and equipment duty rather than optimize coordination in isolation.

Procurement choices affect the result: a different trip unit, fuse, or feeder breaker may change the available coordination range. Ask a direct manufacturer of new distribution assemblies to identify proposed devices and options in the quotation. The specifying engineer should review any substitution against the study and project approval process before it is incorporated.

Turn the study into an executable project package

Provide the manufacturer with the one-line, load and feeder schedules, available fault data, device preferences, coordination objective, and relevant study assumptions. Request a device schedule, applicable published curves or selectivity data, drawings, and a clear list of exceptions. Identify who supplies the coordination study, approves settings, and integrates upstream utility or other equipment information.

Allow time for study updates after device selections, source information, or design revisions change; a late coordination conflict can affect procurement and the lineup design. The final handoff should include approved settings, study results, and as-built device details. Qualified personnel implement and verify settings and perform testing under site procedures and manufacturer instructions before authorized energization.

LET'S BUILD SOMETHING RELIABLE — 03

Ready to talk
switchgear?

Tell us about the new equipment your project needs. Include as much or as little detail as you have today.

(951) 403-5738

CALL TO DISCUSS YOUR PROJECT

PROJECT INQUIRY

Request a quote

01 — 04

This opens your email app for you to review and send. Add any details that do not transfer, or call if you do not have an email app configured.

Request a quote