35 kV Switchgear: Layout and Connection Planning
On a 35 kV system, a switchgear lineup must fit more than the room or pad shown on a drawing.
DIRECT FROM THE MANUFACTURER / NEW EQUIPMENT

THE MANUFACTURER’S PERSPECTIVE — 02
On a 35 kV system, a switchgear lineup must fit more than the room or pad shown on a drawing. Cable size, insulation coordination, access for qualified personnel, and the route into each compartment all shape its design. Owners, engineers, and contractors can reduce redesign by resolving those interfaces with the manufacturer before the layout is frozen. Project-specific engineering review must confirm whether a suitable assembly can be supplied.
Set the electrical envelope first
Give the manufacturer a current one-line showing sources, feeder destinations, system grounding, expected loads, and any planned expansion. Include available fault-current information and protection study requirements. The number of incoming and outgoing circuits affects the lineup, while the protective scheme can influence compartment arrangement and space for instrument transformers.
Nominal system voltage is not automatically the equipment’s maximum voltage class. The project engineer must assess maximum operating voltage, grounding, and the required insulation level, including lightning impulse withstand where specified. Those choices constrain suitable devices, barriers, and terminations; not every assembly is necessarily available for a 35 kV application.
Work backward from the cable termination
For each circuit, identify conductor material, size, insulation, outside diameter, number of parallel cables, and approach direction. The proposed termination type and connector interface matter as much as conductor ampacity. A feeder with several large cables can require a wider or deeper compartment than the single-line symbol suggests.
Coordinate cable bending space, termination height, support points, phase arrangement, and shield or sheath treatment with the cable and termination manufacturers. Top entry may simplify an overhead route but complicate access to other equipment; bottom entry depends on trench or conduit placement. Check both against the actual assembly drawings before civil work is finalized.
Reserve space for access, not just the footprint
Request dimensioned plan and elevation drawings showing doors, removable panels, cable compartments, and any breaker handling or drawout space applicable to the proposed design. The electrical room or outdoor pad must accommodate the equipment and the working and access clearances required by the applicable code, the authority having jurisdiction, and manufacturer instructions.
Also consider the path from the delivery vehicle to the final position: doors, turns, floor loading, lifting height, and overhead obstructions. A compact lineup may save floor area but make cable pulling or future maintenance more difficult. Building, structural, and electrical designers should resolve those competing needs together.
Define grounding, control, and utility boundaries
Show the ground bus connection location and identify who designs the grounding system and cable shield bonding. Shield grounding arrangements depend on the cable system and the engineer’s analysis, not a universal detail. Where a utility supplies or receives power, confirm its requirements for metering, access, protection, and the point of responsibility.
Secondary wiring needs its own physical plan. Specify control power, relay and meter connections, terminal blocks, communications pathways, and any remote indications or commands. Identify which party supplies instrument transformers and external cables. A point list and interface diagram can reveal missing signals before equipment fabrication or site commissioning.
Connect shipping decisions to the site schedule
A long lineup may need shipping splits because of transport limits or the building route. Ask for preliminary section dimensions, weights, lifting provisions, and the expected field assembly interfaces. The contractor and structural engineer can then check rigging, foundation tolerances, anchorage, and whether space remains for sections to be brought together.
Set milestones for drawing approval, cable and termination selection, manufacturing, inspection, delivery, and site readiness. Utility review or a late change in cable size can alter both layout and schedule. For work at an operating facility, the owner and contractor should coordinate outage windows and contingency plans without assuming a fixed delivery date.
Use submittals to close the purchase scope
A useful request for a new assembly includes the one-line, equipment specifications, site drawings, cable schedule, environmental conditions, access constraints, and target milestones. Ask the direct manufacturer to identify proposed construction, interfaces, exclusions, and any exceptions. Confirm the applicable equipment standard and any required listing for the particular design rather than assuming one applies.
Before release, compare approved drawings with the contractor’s conduit, grounding, controls, and foundation plans. Agree on factory inspection or testing criteria, records, manuals, and responsibilities for field connections and acceptance. Installation, verification, and energization belong to qualified personnel under the owner’s safety procedures; a drawing review does not replace that work.