35 kV Switchgear: Procurement and Submittal Checklist
For engineers, contractors, and buyers planning a 35 kV system, a useful request for quotation is more than a voltage label.
DIRECT FROM THE MANUFACTURER / NEW EQUIPMENT

THE MANUFACTURER’S PERSPECTIVE — 02
For engineers, contractors, and buyers planning a 35 kV system, a useful request for quotation is more than a voltage label. A direct American manufacturer needs the electrical design basis, physical interfaces, and approval requirements to evaluate a new assembly. The nominal system voltage alone does not establish the equipment voltage class, insulation level, or availability.
Start with the system design basis
Provide a current one-line diagram showing sources, transformer connections, bus arrangement, switching devices, feeder destinations, and planned expansion. Identify nominal and maximum operating voltage, phase arrangement, frequency, and system grounding. Include utility interface requirements and the responsible engineer’s design assumptions so that bidders are not forced to guess about normal or alternate operating configurations.
Supply available short-circuit study information at the equipment location, including source contributions, relevant X/R ratios, and clearing times for each credible configuration. Identify who will update the study and whether future source changes are included. A single fault-current figure may not describe both the device interrupting duty and the assembly’s time-dependent withstand requirement.
Specify insulation and equipment duty
Ask the project engineer to establish the appropriate equipment maximum voltage class and insulation requirements, including power-frequency and lightning-impulse withstand levels where applicable. Altitude, contamination, grounding, and exposure to switching or lightning transients can affect the selection. Neither a 35 kV system label nor a familiar equipment name proves that a proposed assembly is suitable.
State continuous bus and feeder currents, short-time withstand duty and duration, and the required making and interrupting duties. Request a clear comparison of the proposed devices and assembly ratings against those requirements. A lower-cost device alternative may be attractive, but it is not an equivalent substitution if its insulation, switching duty, or coordination is inadequate.
Define protection and control boundaries
Include a protection one-line and preliminary relay functions, instrument-transformer ratios, accuracy and burden requirements, and the intended protection philosophy. Specify the control-power source, trip and close interfaces, interlocks, alarms, and required indications. The engineer responsible for the coordination study should identify final settings and review compatibility with the selected devices.
For remote monitoring or control, provide the communications protocol, network boundary, point list, and any owner security requirements. Indicate who supplies external wiring, supervisory equipment, and field programming. Separating these responsibilities early helps prevent an apparent equipment saving from becoming an unplanned integration or commissioning expense.
Give bidders the physical interfaces
Submit a dimensioned equipment-room or outdoor site plan showing access routes, installation constraints, cable entry direction, foundation interfaces, and the intended working and maintenance space. State ambient conditions, altitude, moisture, contamination, and any enclosure or seismic criteria. Qualified designers must verify applicable clearances and structural requirements for the actual site and equipment.
Identify conductor quantities, sizes, insulation and shielding details, termination arrangements, grounding connections, and available cable bending space. Coordinate incoming utility and outgoing feeder responsibilities as well as shipping splits, lifting restrictions, and field assembly interfaces. More compact equipment can reduce footprint, but restricted termination and maintenance access may shift difficulty to installation.
Set the submittal and verification checklist
Request an equipment one-line, dimensioned general arrangement, foundation and cable-entry details, device schedule, control schematics, wiring and terminal diagrams, and a list of proposal exceptions. Ask the manufacturer to identify the proposed construction and applicable standards; metal-clad and metal-enclosed descriptions are not interchangeable without reviewing the specified construction and performance.
Define required evidence of design verification, inspection, and factory testing, including agreed functional checks and acceptance criteria. Where a project requires a third-party listing or certification, verify its applicability and scope for the particular assembly. Ask for test records, operation and maintenance information, and final as-built drawings as contractual deliverables.
Plan approvals, sourcing, and handoff
Build the schedule around design review, utility or authority approvals where applicable, component availability, fabrication, testing, shipping, and installation. Identify decision dates and the party responsible for each approval; changes after release can affect both cost and timing. Request a proposal schedule and its assumptions rather than treating an estimate as a delivery guarantee.
Clarify who supplies foundations, primary cables, terminations, relay settings, site testing, and commissioning. If domestic component origin is important, specify the documentation required and confirm actual sourcing and availability for the proposed bill of materials. For projects in San Antonio, South Texas, or elsewhere nationwide, qualified personnel must perform electrical work under site procedures and applicable requirements.