Electrical Interlocks and Controls
An electrical interlock uses control signals to permit or block an equipment action when defined conditions are met.
DIRECT FROM THE MANUFACTURER / NEW EQUIPMENT

THE MANUFACTURER’S PERSPECTIVE — 02
An electrical interlock uses control signals to permit or block an equipment action when defined conditions are met. For a new distribution assembly, the useful specification is not simply “interlocked”: it identifies the devices involved, expected operating states, sources of control power and response to abnormal conditions. Engineers, contractors and facility owners can use that detail to align equipment design with actual operating responsibilities.
Start with the operating philosophy
Describe each power source, incoming device, tie and load on the one-line, then identify which combinations are permitted. For example, a main-tie-main arrangement may be intended to prevent two sources from operating in parallel. Record any approved exceptions and utility conditions rather than assuming every facility has the same transfer philosophy.
An electrical interlock might use device-position contacts and control logic to block an incompatible closing command. Its dependability relies on the selected components, wiring and documented failure response. It is not a substitute for protective devices, safe isolation or a mechanical interlock where the engineered design or project requirements call for one.
Define permissives and control authority
A permissive is a condition that must be satisfied before a requested action is allowed. Depending on the design, conditions may include an acceptable source indication, another device confirmed open, protection relay status or a required time delay. Distinguish a measured source-healthy signal from a breaker-position signal; they answer different questions.
Document who can request an action locally, remotely or automatically, and how those requests are prioritized. Specify expected behavior when position indications disagree, a permissive disappears during a sequence, or an action fails to complete within its allowed time. A state table with inputs, outputs, delays and inhibited commands makes these decisions reviewable.
Account for control and trip power
Identify the supply for each relay, controller, closing circuit, indication and trip circuit, including nominal voltage, polarity where applicable, protection and any external source. A shared control supply can simplify wiring, but a single failure may affect multiple functions. A separate or backed-up supply adds interfaces and must be engineered for the required duty.
The design should state what happens on supply loss, low voltage and restoration. Loss of control power may inhibit closing or compromise a trip function unless the chosen architecture addresses it; do not assume a universal fail-safe position. Assign ownership for batteries, chargers, supply monitoring and field wiring when those items are outside the assembly scope.
Make interface and alarm requirements explicit
Develop a point list for each connection to transfer equipment, generators, building controls or a supervisory system. Identify the signal source and destination, contact type, normal state, terminal designation and responsibility for any external power. For networked points, specify the protocol, data ownership and response to a communication loss.
Differentiate a local indication from an alarm that needs an operator response. Useful examples include control-supply trouble, failed transfer, inconsistent position feedback and a blocked command. Agree on alarm priority, annunciation location, reset authority and the owner’s monitoring requirements; a long point list is not useful if nobody knows what each signal means.
Review failures before selecting components
Walk through credible conditions such as a failed auxiliary contact, broken control wire, stuck output, unavailable source or loss of communications. For each, record the resulting indication, whether a command remains blocked and who must investigate. Consider whether monitoring can distinguish a genuine open position from a missing signal.
Hardwired and programmable logic offer different flexibility, troubleshooting and change-control tradeoffs. Complex sequences can benefit from programmable functions, but their configuration, access controls and revision records become part of the deliverable. The specifying engineer should determine the necessary independence, supervision and mechanical provisions for the consequences of an interlock failure.
Buy the documented sequence, not just hardware
When requesting a quote from a direct manufacturer of new assemblies, provide the one-line, sequence narrative, state table, point list, control-power details and applicable project specifications. Ask for a scope breakdown covering devices, diagrams, software or settings where applicable, terminal interfaces and exceptions. Confirm applicable equipment standards and any project-specific listing requirements.
Agree on review milestones before releasing components: control logic approvals, interface information from other vendors and any witness-test arrangements can affect the schedule. Define factory and site test responsibilities, acceptance criteria and recorded results, including abnormal-state checks. Qualified personnel should perform testing and commissioning under approved procedures; turnover should include revised drawings and operating documentation.